EASTGATEH2V: Key Milestones and Project Phases

EASTGATEH2V is a 6-year project (72 months), running from 2025 to 2031. The project follows a structured, phased approach to deliver Slovakia’s first Hydrogen Valley, ensuring practical results from planning to full-scale operation.

2025

Preparation and Start-up

The project begins with technical planning, permitting processes and detailed design for hydrogen production, distribution and deployment sites.

2026 to 2027

Infrastructure Deployment

Construction starts on the renewable hydrogen production facility near Košice, including installation of 4 MW electrolyser capacity (2 MW Alkaline and 2 MW PEM). Distribution logistics with hydrogen trailers are established.

2027 to 2028

First Hydrogen Applications

Deployment of hydrogen-powered buses, municipal vehicles, and the touristic boat begins. Demonstrations of hydrogen-fuelled VTOL aircraft take place at Košice Airport.

2028 to 2029

Industrial Integration and Cross-border Connections

Green hydrogen is introduced into industrial processes, particularly for high-purity applications. The project enhances Slovakia’s links to Ukraine and integrates into the Central European Hydrogen Corridor.

2030

Full-scale Hydrogen Valley Operation

All hydrogen infrastructure becomes operational. Transport, industrial and mobility applications run at full capacity across the Košice region.

2031

Replication and Knowledge Sharing

The final project year focuses on sharing results, technical insights and socio-economic assessments to support replication of Hydrogen Valleys in other European regions.